| October
8, 2007 |
Outside structure
is all that remains standing of existing Hardee's building. |
|
| October
25, 2007 |
Teardown of the
existing Hardee's structure completed. |
|
| November
5, 2007 |
Volunteer Fire
Fighters and City Members break ground for new fire station. |
|
| March
17, 2008 |
Concrete is broken
up and prepared for recycling. |
|
| March
19, 2008 |
Concrete is removed
and piled for recycling. |
|
| March
26, 2008 |
Recycling of concrete
begins. |
|
| March
28, 2008 |
Dirt moving begins
as concrete is completely ground and piled for later use. |
|
| April
1, 2008 |
Leveling of site
begins, as utilities begin to be installed. |
|
| April
2, 2008 |
Utilities are
being installed. |
|
| April
3, 2008 |
Footings for building
begin to be dug. |
|
| April
8, 2008 |
Footing forms
are erected in the trenches where the footings are to be poured. |
|
| April
12, 2008 |
More footing forms
are installed. |
|
| April
15, 2008 |
Footing cement
poured for part of the footings. |
|
| April
16, 2008 |
Drainage installed. |
|
| April
21, 2008 |
Foundation forms
go up, building steel arrives. |
|
| April
23, 2008 |
Foundation forms
continue to be installed. |
|
| April
25, 2008 |
Part of foundation
is poured. |
|
| April
28, 2008 |
More of the foundation
forms are installed |
|
| April
30, 2008 |
Second foundation
pour is completed. |
|
| May
2, 2008 |
Foundation nears
completion, rain setting back crews. |
|
| May
7, 2008 |
Foundation for
partition wall between office area and bays being set. |
|
| May
9, 2008 |
Foundation for
partition wall between office area and bays poured, and last section
of foundation is formed. |
|
| May
12, 2008 |
Apparatus bay
sidewall steel starting to be put in place. |
|
| May
14, 2008 |
Completion of
the apparatus bay sidewall steel and starting roof supports. |
|
| May
16, 2008 |
Roof supports
near completion. |
|
| May
20, 2008 |
Wall panels start to be put in place.
|
|
| May
22, 2008 |
More wall panels installed.
|
|
| May
28, 2008 |
Partition wall
between apparatus bay and office area begins. |
|
| May
30, 2008 |
Partition wall
between apparatus bay and office area nears completion. |
|
| |
Roof goes on office
area |
|
| June
5, 2008 |
Electrical box foundation poured, canopy footings
poured
|
|
| June 10, 2008 |
Office roof work continues
|
 |
| June 12, 2008 |
Canopy foundations are poured, mezanine footings are
poured |
 |
| June 16, 2008 |
In floor heat tubing is layed in office area, and
beginning in bay area |
 |
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|