| October
8, 2007 |
Outside structure
is all that remains standing of existing Hardee's building. |
|
| October
25, 2007 |
Teardown of the
existing Hardee's structure completed. |
|
| November
5, 2007 |
Volunteer Fire
Fighters and City Members break ground for new fire station. |
|
| March
17, 2008 |
Concrete is broken
up and prepared for recycling. |
|
| March
19, 2008 |
Concrete is removed
and piled for recycling. |
|
| March
26, 2008 |
Recycling of concrete
begins. |
|
| March
28, 2008 |
Dirt moving begins
as concrete is completely ground and piled for later use. |
|
| April
1, 2008 |
Leveling of site
begins, as utilities begin to be installed. |
|
| April
2, 2008 |
Utilities are
being installed. |
|
| April
3, 2008 |
Footings for building
begin to be dug. |
|
| April
8, 2008 |
Footing forms
are erected in the trenches where the footings are to be poured. |
|
| April
12, 2008 |
More footing forms
are installed. |
|
| April
15, 2008 |
Footing cement
poured for part of the footings. |
|
| April
16, 2008 |
Drainage installed. |
|
| April
21, 2008 |
Foundation forms
go up, building steel arrives. |
|
| April
23, 2008 |
Foundation forms
continue to be installed. |
|
| April
25, 2008 |
Part of foundation
is poured. |
|
| April
28, 2008 |
More of the foundation
forms are installed |
|
| April
30, 2008 |
Second foundation
pour is completed. |
|
| May
2, 2008 |
Foundation nears
completion, rain setting back crews. |
|
| May
7, 2008 |
Foundation for
partition wall between office area and bays being set. |
|
| May
9, 2008 |
Foundation for
partition wall between office area and bays poured, and last section
of foundation is formed. |
|
| May
12, 2008 |
Apparatus bay
sidewall steel starting to be put in place. |
|
| May
14, 2008 |
Completion of
the apparatus bay sidewall steel and starting roof supports. |
|
| May
16, 2008 |
Roof supports
near completion. |
|
| May
20, 2008 |
Wall panels start to be put in place.
|
|
| May
22, 2008 |
More wall panels installed.
|
|
| May
28, 2008 |
Partition wall
between apparatus bay and office area begins. |
|
| May
30, 2008 |
Partition wall
between apparatus bay and office area nears completion. |
|
| |
Roof goes on office
area |
|
| June
5, 2008 |
Electrical box foundation poured, canopy footings
poured
|
|
| June 10, 2008 |
Office roof work continues |
 |
| June 12, 2008 |
Canopy foundations are poured, mezzanine footings
are poured |
 |
| June 16, 2008 |
In floor heat tubing is installed in office area,
and beginning in bay area |
 |
| June 19, 2008 |
In floor heat continues to be installed
in offices and bay area |
 |
| June 24, 2008 |
Mezzanine beams are delivered and roof
steel is beginning to be installed |
 |
| June 26, 2008 |
Office enclosed and floor conrete is
poured |
 |
| July 5, 2008 |
Mezzanine steel is set, and office
wall studs are installed |
 |
July 10, 2008 |
In floor heat in bays continues, utilities
in office area begin to be installed in walls |
 |
| July 14, 2008 |
In floor heat in bays nears completion
and exterior sheeting on upper bay walls is installed |
 |
| July 24, 2008 |
Concrete floor is poured in bay area,
and sheetrock begins in office area |
 |
| August 12, 2008 |
Office completely closed in and drywall
seam taping begins, work on mezzanine floor begins |
 |
| August 20, 2008 |
Office windows are installed, mezzanine
floor complete and mezzanine walls begin |
 |
| September 3, 2008 |
Front entry door installed, bay doors
installed, and retaining wall to north edge of property is completed |
 |
| September 21, 2008 |
Concrete driveways and sidewalks are
poured, interior painting and finish work begins |
 |
| October 26, 2008 |
Interior finish work nears completion,
furniture and other interior items installed and delivered |
 |
| November 1, 2008 |
Moving day finally arrives |
 |
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|